BEIKE NEW MATERIAL

Loyang Wanji Aluminum Processing Co., Ltd. Intelligent Logistics Management System High-Bay Warehouse

Structural Form: Steel gantry structure, intelligent three-dimensional warehouse, steel consumption 4327 tons. Project Address: Xin'an County, Luoyang City, Henan Province Construction Unit: Luoyang Wanji Aluminum Processing Co., Ltd. Design Unit: SMS-SIEMAG GmbH, Germany Project Overview: Mainly used for storing, transferring, and cooling aluminum coils, as well as coordinating and managing the transportation of coils between cold rolling mills and finishing equipment. This high-bay warehouse is 276.89m long and 17.8m wide. The building height is 29.7m. The structure is a double-channel 3-column 6-layer rack, with a total of 1393 coil positions. The maximum coil diameter is Φ2800mm (including the inner core diameter), weighing 33.8T; the minimum coil diameter is Φ1200mm. The maximum temperature of aluminum coils entering the high-bay warehouse is 320°C (Fahrenheit), and the normal temperature inside the warehouse is controlled below 28°C (Fahrenheit).


Structure: Steel frame structure, intelligent three-dimensional warehouse, steel consumption 4327 tons.

Project Address: Xin'an County, Luoyang City, Henan Province

Construction Unit: Luoyang Wanji Aluminum Processing Co., Ltd.

Design Unit: SMS-SIEMAG GmbH, Germany

Project Overview: Mainly used for storing, transferring, and cooling aluminum coils, as well as coordinating and managing the transportation of coils between cold rolling mills and finishing equipment. This high-bay warehouse is 276.89m long and 17.8m wide. The building height is 29.7 meters. The structure is a double-channel 3-column 6-layer rack, with a total of 1393 coil positions. The maximum coil diameter is Φ2800mm (including the inner drum diameter), weighing 33.8T; the minimum coil diameter is Φ1200mm, and the maximum temperature of aluminum coils entering the high-bay warehouse is 320°C (Fahrenheit), and the normal temperature inside the warehouse is controlled below 28°C (Fahrenheit).

undefined

NEW Relocation of the old plant and isocyanate integration project of Yantai Wanhua Polyurethane Co., Ltd.

Relocation of the old plant and isocyanate integration project of Yantai Wanhua Polyurethane Co., Ltd.

Structural Form: Primarily steel frame structure Project Location: Yantai, Shandong Province Construction Unit: Wanhua Chemical Group Co., Ltd. Design Unit: Hualu Engineering Technology Co., Ltd. Project Overview: The total steel volume of this project is 24,200 tons, consisting of multiple project unit structures. It mainly includes steel frame structures for methanol synthesis units, ammonia refrigeration units, raw material storage and preparation units, methanol rectification, wastewater systems, low-temperature methanol washing, main methanol units, nitric acid units, formaldehyde tank areas, and auxiliary walkways.
NEW Lanzhou Donggang Interchange Project

Lanzhou Donggang Interchange Project

General Contractor: China Railway 21st Bureau Group Fifth Engineering Construction Co., Ltd. Design Institute: Shanghai Urban Construction Design & Research Institute (Group) Co., Ltd. Project Overview: This project is the demolition and reconstruction of the Donggang Overpass in Lanzhou City. The main bridge is a continuous steel box girder with spans of 23m+42m+35m+30m, a standard deck width of 25.5m, a girder height of 1.8m, and a total weight of 1050 tons. The construction method is the overall top-push sliding method, with a total jacking length of 51 meters.
NEW Longhai Road Elevated Road Project

Longhai Road Elevated Road Project

Project Location: Zhengzhou, Henan Province Project Overview: Approximately 21.5KM in total length. The elevated bridge starts from the west of the West Third Ring Road, then shifts south after reaching Weilai Road, continues eastward along Huozhan Street, and finally intersects with the Beijing-Hong Kong-Macau Expressway. The height of the steel box girder of the No. 3 section ramp is 2-2.2 meters, with a bridge width of 9-11 meters, and a single-box double-cell section. The height of the No. 43 section rigid box girder of the main line in section No. 5 is 2 meters, with a bridge width of 35-40.1 meters. The total project volume is 4300 tons.